Annual Sanitary Sewer Rehabilitation Project

​​Project Overview: ​EU-0178

Annual program for replacement and rehabilitation of sanitary sewer mains and manholes via open-trench and trenchless methods. This project will rehabilitate or replace sewer mains and manholes which are deteriorated or have reached the end of their service life. The program also includes elements to reduce or eliminate stormwater inflow and groundwater infiltration into the sanitary sewer system, reducing flow volumes to the City's Waste Water Treatment Plant.

Funding from the City Sewer Fund.

​Status - June 2020

Accomplishments:​ Construction continuing. Hilton Avenue and Berry Street sections pipe installation has been completed. 

Next Milestone: ​CIPP beginning early July. Cedar Street, Grove Street, and Alley north of Connecticut Street pipe installation anticipated for July-August 2020. 

Project Details

  • Status - Construction​​
  • Contract Awarded - 2/10/2020
  • Contract Amount - $1,595,621.43
  • Contractor - Faber Construction
  • Anticipated Completion Date - Late August or​ early September 2020
  • Vicinity Map​​

Affected Neighborhoods

    City Center; Cornwall Park; Sehome; South Hill; Western Washington University

Participating Departments

    Public Works